Project Details
Contracter:
Green Oasis General Contracting
Date:
December 2020 to October 2022
Nature Of Work:
• Installation and welding of Underground and Above Ground CS pipeline diameter 64/56”
• Pipe installation & welding for air vent, wash out and line valve chambers.
• Pipe installation and welding in tank area.
• Hydrostatic test, Dis-Infection & Flushing.
• Valves installation & Bolting works in washout & Tap-off chambers.